Progress on site

  • 21 April 2016
    Update – Shops and Offices
    The video of the completed Imperial and Whitehall offices can be viewed by following this link. The shop fronts are now in place with the finishing touches being carried out. We have secured a number of exciting tenants for the retail units and are in discussions with several more.  We will start handing the units over to […]
  • 21 April 2016
    Update – New Core and Terrace
    The drainage works are complete.  The first section of the steel frame has now been created.  The lift base is in the process of being cast.    
  • 21 April 2016
    Update – Barwick Street Facade
    The works are now complete.  The scaffolding has been removed.  The small section of scaffolding will remain so the tower crane can lift materials from Barwick Street.  
  • 21 April 2016
    Update – Roof
    All of the roof works are now complete and all of the scaffolding has been removed.
  • 1 February 2016
    Barwick Street Façade – Update January 2016
    The snagging process has commenced with the first sections of scaffold removed in Barwick Street.  The internal courtyard elevation will be next followed by the remaining Barwick Street sections over the next 4 weeks.
  • 1 February 2016
    Shops and Offices – Update January 2016
    The offices are now finished and ready for letting and had their official launch on 20th January 2016. They have been named Imperial and Whitehall, some images can be found at http://imperialandwhitehall.co.uk/ The shop works are progressing, but issues with the building are still being discovered.  The shop fronts are progressing well with the timber […]
  • 1 February 2016
    Roof – Update January 2016
    The roof works have now reached practical completion.  All of the access scaffold will be removed over the next 3-4 weeks.
  • 1 February 2016
    Façade – Update January 2016
    All the works to the façade are now complete. The “Grand Hotel” signage was successfully tested.  This has received a positive response from those that saw it.
  • 1 February 2016
    New Core and Terrace – Update January 2016
    The completion of the drainage works has been slightly delayed following the discovery of an underground water storage tank.  These works should be complete within the next 4 weeks.  
  • 1 November 2015
    Update – Shops and Offices
    Works are progressing very well to the second floor offices with the first floor not far behind. Works to the shops still prove challenging but we have now designed and commenced with the structural repairs to the floors, thus enabling the new shop fronts to be installed in early 2016.