    Façade – Update January 2016
    All the works to the façade are now complete. The “Grand Hotel” signage was successfully tested.  This has received a positive response from those that saw it.
  • 1 February 2016
    New Core and Terrace – Update January 2016
    The completion of the drainage works has been slightly delayed following the discovery of an underground water storage tank.  These works should be complete within the next 4 weeks.  
  • 1 February 2016
    Grand Offices
    Hortons’ Estate has unveiled 10,000 sq ft of refurbished Grade A office space at The Grand, 23 Colmore Row, Birmingham. The family owned property company has invested more than £1.5million creating the new office suites, which range in size from 183 sq ft – 2,874 sq ft, with potential to combine some of the suites […]
  • 27 January 2016
    A GRAND VENTURE FOR BAR OPERATOR
      Hortons’ Estate Ltd has completed the lettings of three more retail units at The Grand, on Birmingham’s Colmore Row. Restaurant and bar operator Living Ventures is bringing its GUSTO and The Alchemist brands to Birmingham, following the opening of its first bar and restaurant in the city, The Botanist, on Temple Street, last year. […]
  • 22 December 2015
    Shoemaker Steps back to the Grand
        Hortons’ Estate Ltd has signed up the first retail tenant at the newly restored The Grand on Colmore Row in Birmingham.   Shoemaker Crockett & Jones is moving back to its former store on the ground floor of the building having agreed a new ten-year lease.   Crockett & Jones opened its first […]
  • 8 December 2015
    Radio WM Interview with Chief Executive
    An interview with Hortons’ Estate’s Chief Executive, Tony Green.
  • 24 November 2015
    £6 MILLION BOOST FOR THE GRAND
    The Greater Birmingham and Solihull Local Enterprise Partnership and Birmingham City Council have agreed to provide £6million of grant support towards the cost of interior works at The Grand Hotel, 1 Church Street, Birmingham. The work to the hotel will complete the restoration of the Grade II* Grand block, following on from £14million of works […]
  • 1 November 2015
    Update – Shops and Offices
    Works are progressing very well to the second floor offices with the first floor not far behind. Works to the shops still prove challenging but we have now designed and commenced with the structural repairs to the floors, thus enabling the new shop fronts to be installed in early 2016.
  • 1 November 2015
    Update – Barwick Street Facade
    These works are nearing completion, with the snagging process due to commence in mid November.  It is our hope to have all the scaffolding down in Barwick Street by the end of December.  
  • 1 November 2015
    October Update – Facade
    All of the scaffolding to Colmore Row has now been removed and the final bits of stone replacement are completed.  There is only a small section on Church Street left to restore.  This should all be completed shortly. We are due to test the signage, in red,  on 11th November to coincide with Armistice Day […]