IMG_0083

The original roof structure is now removed  with only a few timber members remaining to provide continued support to the building elevations.

 Work has commenced to rebuild sections of damaged brickwork and also to install the padstones  which will eventually take the weight of the new steel structure.

 

IMG_0121 IMG_0077

Temporary “Trad” deck flooring is now being installed to allow for a safe working platform for when the new steelwork arrives.

Take a look at February’s time lapse footage.

video